Perplex
Dashboard
Topics
Exponents & LogarithmsApproximations & ErrorSequences & SeriesMatricesComplex NumbersFinancial Mathematics
Cartesian plane & linesFunction TheoryModellingTransformations & asymptotes
2D & 3D GeometryVoronoi DiagramsTrig equations & identitiesVectorsGraph Theory
ProbabilityDescriptive StatisticsBivariate StatisticsDistributions & Random VariablesInference & Hypotheses
DifferentiationIntegrationDifferential Equations
Review VideosFormula BookletMy Progress
BlogLanding Page
Sign UpLogin
Perplex
Perplex
Dashboard
Topics
Exponents & LogarithmsApproximations & ErrorSequences & SeriesMatricesComplex NumbersFinancial Mathematics
Cartesian plane & linesFunction TheoryModellingTransformations & asymptotes
2D & 3D GeometryVoronoi DiagramsTrig equations & identitiesVectorsGraph Theory
ProbabilityDescriptive StatisticsBivariate StatisticsDistributions & Random VariablesInference & Hypotheses
DifferentiationIntegrationDifferential Equations
Review VideosFormula BookletMy Progress
BlogLanding Page
Sign UpLogin
Perplex

Inference & Hypotheses (Lesson 5/6)

Z-test and Confidence Intervals

1 / 20

Discussion

A machine cuts precision parts for use in airplanes. The time, ​X​ seconds, taken to cut each part is normally distributed with a standard deviation of ​12, but known mean:

​
X∼N(μ,122)
​

The quality control engineer samples the time taken to manufacture ​8​ parts:

​
45,47,49,51,53,55,57,59
​

(a)

What's the best guess the engineer can make for the average ​μ?

Solution:

The machine’s average cutting time is unknown, so the best single guess is the sample average. With the eight times 45, 47, 49, 51, 53, 55, 57, 59, notice they are evenly spaced and symmetric about the midpoint. So the average is the midpoint of the smallest and largest:

​
xˉ=245+59​=52
​

Inference & Hypotheses (Lesson 5/6)

Z-test and Confidence Intervals

1 / 20

Discussion

A machine cuts precision parts for use in airplanes. The time, ​X​ seconds, taken to cut each part is normally distributed with a standard deviation of ​12, but known mean:

​
X∼N(μ,122)
​

The quality control engineer samples the time taken to manufacture ​8​ parts:

​
45,47,49,51,53,55,57,59
​

(a)

What's the best guess the engineer can make for the average ​μ?

Solution:

The machine’s average cutting time is unknown, so the best single guess is the sample average. With the eight times 45, 47, 49, 51, 53, 55, 57, 59, notice they are evenly spaced and symmetric about the midpoint. So the average is the midpoint of the smallest and largest:

​
xˉ=245+59​=52
​